Relating to: renewable energy portfolio standards.

Cooperative associations Electric utility Electricity Energy conservation

  1. Introduced, completed
  2. Passes Assembly, completed
  3. Passes Senate, completed
  4. Governor signs, completed
  5. Law, completed

Unfamiliar terms? Glossary

What this bill does

Plain-language analysis by the nonpartisan Legislative Reference Bureau

Under current law, electric utilities and retail electric cooperatives (electric

providers) are required to ensure that, in a given year, a specified percentage of the

electricity that the utility or cooperative sells to customers is renewable energy.

These requirements are commonly referred to as renewable portfolio standards

(RPSs), and they include deadlines that apply to an electric provider's renewable

energy percentage (REP). In general, an electric provider's REP for a particular year

is the percentage that results from dividing the renewable energy sold in year,

augmented by certain credits, by the total electricity sold in that year. For the year

2009, current law prohibited an electric provider from decreasing its REP below its

baseline renewable percentage (BRP), which is defined as the average of the electric

provider's REP for 2001, 2002, and 2003. For the year 2010, current law required

an electric provider to increase its REP at least two percentage points above its BRP.

For the years 2011 to 2014, current law prohibits an electric provider from decreasing

its REP below the percentage required in 2010. For the year 2015, current law

requires an electric provider to increase its REP at least six percentage points above

its BRP, and for each year thereafter, current law prohibits an electric provider from

decreasing its REP below the percentage required in 2015.

This bill creates an exception to the above requirements for the years 2015 and

thereafter. The exception applies to an electric provider whose BRP exceeds 12

percent and whose REP for the year 2014 exceeds 14 percent. Under the bill, an

electric provider who qualifies for the exception must maintain its REP in the years

2015 and thereafter at a level that is at least two percentage points above its BRP.

Sponsors

Introduced by: Kahl (D) , Krug (R) , Kuglitsch (R) , Kulp (R) , Severson (R) , T. Larson (R)

6 cosponsors

Farrow (R) , Grothman (R) , Lassa (D) , Petrowski (R) , Shankland (D) , Wright, Barca, Bewley and Zepnick

Votes

Assembly: Report passage recommended by Committee on Energy and Utilities, Ayes 10, Noes 0

Passed 10–0 Jan 16, 2014 official source full page

No individual roll call was recorded for this vote. Committee votes and some older sessions record totals only.

Full history

  1. Jan 3, 2014 · Assembly

    Introduced by Representatives Krug, Kuglitsch, Kulp, Severson, T. Larson and Kahl; cosponsored by Senators Farrow, Petrowski, Grothman and Lassa

  2. Jan 3, 2014 · Assembly

    Read first time and referred to Committee on Energy and Utilities

  3. Jan 9, 2014 · Assembly

    Public hearing held

  4. Jan 9, 2014 · Assembly

    Representative Shankland added as a coauthor

  5. Jan 15, 2014 · Assembly

    Executive action taken

  6. Jan 16, 2014 · Assembly

    Report passage recommended by Committee on Energy and Utilities, Ayes 10, Noes 0

  7. Jan 16, 2014 · Assembly

    Referred to Committee on Rules

  8. Jan 16, 2014 · Assembly

    Placed on calendar 1-21-2014 by Committee on Rules

  9. Jan 21, 2014 · Assembly

    Rules suspended

  10. Jan 21, 2014 · Assembly

    Read a third time and passed

  11. Jan 21, 2014 · Assembly

    Representatives Wright, Barca, Bewley and Zepnick added as coauthors

  12. Jan 21, 2014 · Assembly

    Ordered immediately messaged

  13. Jan 21, 2014 · Senate

    Received from Assembly

  14. Jan 21, 2014 · Assembly

    Read a second time

  15. Jan 21, 2014 · Assembly

    Ordered to a third reading

  16. Jan 22, 2014 · Senate

    Read first time and referred to committee on Senate Organization

  17. Jan 22, 2014 · Senate

    Rules suspended to withdraw from committee on Senate Organization and take up

  18. Jan 22, 2014 · Senate

    Read a second time

  19. Jan 22, 2014 · Senate

    Ordered to a third reading

  20. Jan 22, 2014 · Senate

    Rules suspended

  21. Jan 22, 2014 · Senate

    Read a third time and concurred in

  22. Jan 22, 2014 · Senate

    Ordered immediately messaged

  23. Jan 22, 2014 · Assembly

    Received from Senate concurred in

  24. Feb 4, 2014 · Assembly

    Report correctly enrolled on 2-4-2014

  25. Apr 15, 2014 · Assembly

    Presented to the Governor on 4-15-2014

  26. Apr 16, 2014 · Assembly

    Report approved by the Governor on 4-16-2014. 2013 Wisconsin Act 290

  27. Apr 16, 2014 · Assembly

    Published 4-17-2014