Bills · 2013-2014 Regular Session
Relating to: Public Service Commission certificates for certain activities; tampering with telecommunications or electric wires; regulation of pay telephone service providers and cable television telecommunications service providers; accident reporting by telecommunications utilities; the definition of transmission facility; availability of public utility rate schedules; and rule-making procedures.
Administrative rules Administrative rules — Bill to suspend existing rule _s.227.26 _2_f_ Electric utility Electricity Public service commission Public service commission — Administrative rules Public utility Telecommunications Telephone Television
- Introduced, stopped here
- Passes Senate, not reached
- Passes Assembly, not reached
- Governor signs, not reached
- Law, not reached
Unfamiliar terms? Glossary
What this bill does
Plain-language analysis by the nonpartisan Legislative Reference Bureau
This bill makes changes regarding all of the following: 1) Public Service
Commission (PSC) certificates required for certain activities; 2) filing requirements
for public utility rate schedules; 3) water public utility rate changes; 4)
telecommunications regulation; 4) legislative repeal or modification of agency rules;
and 5) tampering with telecommunications or electric wires.
PSC certificates.
Current law prohibits a public utility from beginning
construction or providing service in a municipality, unless the public utility obtained
a certificate from the PSC authorizing the public utility to transact public utility
business. Current law also prohibits a public utility from beginning certain projects
involving new or existing plants, equipment, property, or facilities, unless the public
utility has complied with applicable PSC rules and orders. In addition, current law
allows the PSC to prohibit a public utility from proceeding with such a project until
the PSC certifies that public convenience and necessity require the project. Current
law also includes exemptions that are based on the gross cost of the project and the
type of public utility that proposes the project. The bill provides that those
exemptions do not apply to the first prohibition described in the foregoing, but do
apply to the second and third prohibitions.
Current law also generally prohibits a person from commencing construction
of certain large electric generating facilities or high-voltage transmission lines
without obtaining a certificate of public convenience and necessity (CPCN) from the
PSC. After a person files an application for a CPCN, the PSC must determine
whether the application is complete. If the PSC fails to make such a determination
within a specified deadline, the application is considered to be complete. Current law
requires the PSC to take final action on the application within 180 days after the
application is determined or considered to be complete. If the PSC fails to take final
action within that deadline, the PSC is considered to have issued a CPCN to the
applicant. However, current law also allows the PSC to petition the circuit court for
Dane County for an extension of the deadline for no more than an additional 180
days. Upon a showing of good cause, the court may extend the deadline. If the PSC
fails to take final action within the extended deadline, the PSC is considered to have
issued the CPCN. The bill eliminates the requirement for the PSC to petition the
court for a deadline extension. Instead, the bill allows the chairperson of the PSC
to extend the deadline for no more than an additional 180 days for good cause. As
under current law, if the PSC fails to take final action within the extended deadline,
the PSC is considered to have issued the CPCN.
Public utility rate schedules.
Under current law, certain public utilities
must file schedules with the PSC showing their rates for service. Current law
requires the PSC to determine the portion of a public utility's rate schedule that is
Sponsors
Votes
Senate: Report passage recommended by Committee on Government Operations, Public Works, and Telecommunications, Ayes 7, Noes 0
Passed 7–0 Jan 22, 2014 official source full pageNo individual roll call was recorded for this vote. Committee votes and some older sessions record totals only.
Full history
- Jan 6, 2014 · Senate
Introduced by Senators Cowles, Farrow and Schultz; cosponsored by Representatives Kuglitsch, Bies, Kulp, Kahl, Ohnstad and Petryk
- Jan 6, 2014 · Senate
Read first time and referred to Committee on Government Operations, Public Works, and Telecommunications
- Jan 9, 2014 · Senate
Public hearing held
- Jan 22, 2014 · Senate
Executive action taken
- Jan 22, 2014 · Senate
Report passage recommended by Committee on Government Operations, Public Works, and Telecommunications, Ayes 7, Noes 0
- Jan 22, 2014 · Senate
Available for scheduling
- Apr 8, 2014 · Senate
Failed to pass pursuant to Senate Joint Resolution 1