Bills · 2013-2014 Regular Session
Relating to: procedures for utility projects that require a permit from the Department of Natural Resources. (FE)
Cooperative associations Electric utility Electricity Natural resources, department of — Environmental protection Natural resources, department of — Hunting and fishing Public service commission Public utility Shoreland zoning Waterways and water power
- Introduced, stopped here
- Passes Senate, not reached
- Passes Assembly, not reached
- Governor signs, not reached
- Law, not reached
Unfamiliar terms? Glossary
What this bill does
Plain-language analysis by the nonpartisan Legislative Reference Bureau
This bill changes the procedures for obtaining permits from the Department of
Natural Resources (DNR) for utility facilities that undertake construction activities
affecting navigable waters. The bill also exempts certain utility projects from
requirements to obtain permits from DNR and from certain shoreland zoning
ordinances.
Procedures under current law
Under current law, with certain exceptions, a public utility may not begin
construction on a utility project unless the Public Service Commission (PSC) has
issued a certificate for the project. A public utility is a company or political
subdivision that produces or delivers heat, light, water, or power to or for the public.
Current law also prohibits any person, including a public utility, from constructing
a large electric generating facility or a high-voltage transmission line (electric
facility) without another type of certificate from the PSC. Current law also generally
requires a person, including a public utility or electric facility (utility), to obtain a
permit from DNR before engaging in an activity affecting navigable waters. Those
permits include permits for the placement of a structure in navigable waters, for the
construction or maintenance of a dam, or for activities affecting a wetland (DNR
permits). Generally, under current law, a person must submit an application to DNR
for each required permit. If the applicant is a utility that is required to obtain a
certificate from the PSC, however, the utility must submit a single application to
DNR requesting all of the DNR permits that the utility requires for a given project
affecting navigable waters (utility application) and must follow a different procedure
for obtaining these DNR permits (utility application procedure).
Under current law, a person proposing to submit a utility application to DNR
must first notify DNR of the intention to file that application. After DNR receives
the notice, DNR must confer with that person and, in cooperation with the PSC,
make certain assessments and analyses concerning the project. Once the utility
application is complete, DNR may schedule the matter for a public hearing. DNR
must grant or deny the application within 30 days of the date on which the PSC
issues its decision on the utility's application for a certificate.
Current law also specifies that as a part of the utility application procedure,
DNR must review the proposed utility project to assess whether the location, site, or
route is capable of meeting the criteria for obtaining the required DNR permits and
must provide this information to the PSC. DNR must also participate in PSC
investigations or proceedings relating to the application for a certificate for the
utility project. If the PSC issues the certificate for that utility project, after
considering DNR's participation in the PSC's proceedings and after considering
certain other factors, DNR may not require the applicant to make any further
analysis of project alternatives, except that DNR may identify adjustments that may
be required to address permitting issues within the location, site, or route for which
What it would cost
Fiscal estimates filed by state agencies, as official PDFs
Sponsors
Full history
- Feb 20, 2014 · Senate
Introduced by Senators Tiffany, Harsdorf and Moulton; cosponsored by Representatives T. Larson, Bernier, Bewley, Brooks, Knudson, Kulp, Marklein, Murtha, A. Ott, Petryk, Severson, Smith, Thiesfeldt, Vruwink, Wachs and Williams
- Feb 20, 2014 · Senate
Read first time and referred to Natural Resources
- Mar 3, 2014 · Senate
Fiscal estimate received
- Mar 3, 2014 · Senate
Fiscal estimate received
- Apr 8, 2014 · Senate
Failed to pass pursuant to Senate Joint Resolution 1