Bills · 2023-2024 Regular Session
Relating to: expenditure of $213,302.77 from the general fund in payment of a claim against the state made by JRT Top Notch Roofs, LLC. (FE)
Administration department of — Budget and fiscal issues Claims Collective bargaining
- Introduced, stopped here
- Passes Assembly, not reached
- Passes Senate, not reached
- Governor signs, not reached
- Law, not reached
Unfamiliar terms? Glossary
What this bill does
Plain-language analysis by the nonpartisan Legislative Reference Bureau
This bill directs the expenditure of $213,302.77 from the general fund in
payment of a claim against the Department of Administration by JRT Top Notch
Roofs, LLC. The claimant entered into a contract with DOA to replace the roof of
Esker Hall at the University of Wisconsin-Whitewater. The claimant asserts that
the bid documents stated that the project would begin “on or before” a date provided
in the notice to proceed and that the notice to proceed stated that the project would
begin “on or before” May 17, 2021. The claimant claims that the claimant submitted
a tentative schedule with a start date of April 5, 2021, which was rejected by DOA.
The claimant asserts that the later start date affected its ability to acquire project
materials in a timely manner and that DOA refused to negotiate the start date in
good faith. The claimant claims that, despite its best efforts to meet DOA demands,
DOA stopped communicating with the claimant and terminated the contract. The
claimant asserts that the schedules it proposed were contractually compliant and
that DOA had no right to terminate the contract. The claimant demands that DOA
rescind the contract termination and reinstate the claimant on the project.
Alternatively, if the claimant is not allowed to complete the project, the claimant
requests $213,302.77 in lost revenue. DOA concedes that the notice to proceed
inadvertently stated that work would begin “on or before” May 17, 2021. However,
DOA maintains that the contract signed by the claimant stated that work was to
begin “on or after” the date specified in the notice to proceed, that the bid documents
clearly stated that mobilization was not scheduled to take place until June 2021, and
that any alleged confusion was resolved when DOA informed the claimant that it
would not be permitted to mobilize until May 17, 2021. To the extent there was any
confusion in the bid documents, DOA asserts that bidders were to notify DOA prior
to the bid opening, which the claimant did not do. In response to the claimant's
concerns about procuring materials, DOA asserts that it proposed extending the
completion deadline by 16 days. DOA further notes that the contract allowed the
claimant to obtain and request reimbursement for offsite materials storage. DOA
maintains that any difficulties obtaining project materials were caused by the
claimant's failure to purchase those materials in a timely manner. On July 21, 2022,
the claims board denied the claim because it concluded that the claim raises
questions of fact that are better evaluated by a court of law (see 2021
Senate Journal
,
p. 975).
Sponsors
Introduced by: Brooks (R)
Full history
- Mar 22, 2024 · Assembly
Introduced by Representative Brooks
- Mar 22, 2024 · Assembly
Read first time and referred to Committee on State Affairs
- Apr 15, 2024 · Assembly
Failed to pass pursuant to Senate Joint Resolution 1