Bills · 2023-2024 Regular Session

AB 470

Died at session end Official bill text Atom feed

Relating to: an incumbent transmission facility owner's right to construct, own, and maintain certain transmission facilities and Public Service Commission procedures if the transmission facility is a regionally cost-shared transmission line.

Electric utility Public service commission

  1. Introduced, stopped here
  2. Passes Assembly, not reached
  3. Passes Senate, not reached
  4. Governor signs, not reached
  5. Law, not reached

Unfamiliar terms? Glossary

What this bill does

Plain-language analysis by the nonpartisan Legislative Reference Bureau

This bill grants to an incumbent transmission facility owner the right to

construct, own, and maintain a transmission facility that has been approved for

construction in the Midcontinent Independent System Operator's (MISO)

transmission plan and that connects to transmission facilities owned by that

incumbent transmission facility owner. Under the bill, an “incumbent transmission

facility owner” is a transmission company or a cooperative or public utility that owns

a transmission facility and provides transmission service in this state. Under

current law, MISO is an organization that is subject to the jurisdiction of the Federal

Energy Regulatory Commission and that coordinates and controls electric

transmission in a region of the country that includes this state. The bill provides that

the right to construct, own, and maintain a transmission facility that connects to

transmission facilities owned by two or more incumbent transmission facility owners

belongs individually and proportionally to each incumbent transmission facility

owner, unless otherwise agreed upon in writing.

The bill also defines “regionally cost-shared transmission line” to mean a

high-voltage transmission line that is eligible for regional cost sharing and is not

subject to a right of first refusal in accordance with the MISO tariff. Under the bill,

if under MISO's transmission plan a regionally cost-shared transmission line has

been approved for construction and connection to facilities owned by an incumbent

transmission facility owner, the incumbent transmission facility owner must give

the Public Service Commission written notice regarding the owner's intent to

construct, own, and maintain the line no later than 90 days after approval of the

transmission plan. If the owner indicates that it does not intent to construct the line,

the bill requires it to fully explain that decision in the notice to PSC. In that case,

the bill allows PSC to determine whether the incumbent transmission facility owner

or another entity must construct the line, taking into consideration issues such as

cost, efficiency, and reliability.

The bill requires an incumbent transmission facility owner with the right to

construct a MISO-approved regionally cost-shared transmission line to include in

any application for a certificate of public convenience and necessity an estimate of

the cost of construction, along with documentation that the estimate is the result of

competitively bid engineering, procurement, and construction contracts. The bill

also requires such an incumbent transmission facility owner to provide to PSC until

construction is complete quarterly reports that include updated estimates of the

construction cost and an explanation of any changes from prior cost estimates.

Sponsors

Introduced by: Mursau (R) , O'Connor (R) , Petersen (R) , Steffen (R) , Swearingen (R) , Wichgers (R)

4 cosponsors

Bradley (R) , Marklein (R) , Subeck (D) , Wanggaard (R)

Votes

Assembly: Report passage recommended by Committee on Energy and Utilities, Ayes 12, Noes 4

Passed 12–4 Feb 13, 2024 official source full page

No individual roll call was recorded for this vote. Committee votes and some older sessions record totals only.

Full history

  1. Oct 5, 2023 · Assembly

    Introduced by Representatives Petersen, Mursau, O'Connor, Plumer, Steffen, Swearingen and Wichgers; cosponsored by Senators Bradley, Marklein and Wanggaard

  2. Oct 5, 2023 · Assembly

    Read first time and referred to Committee on Energy and Utilities

  3. Oct 10, 2023 · Assembly

    Public hearing held

  4. Oct 11, 2023 · Assembly

    Representative Plumer withdrawn as a coauthor

  5. Oct 31, 2023 · Assembly

    Assembly Amendment 1 offered by Representative Tranel

  6. Nov 1, 2023 · Assembly

    Executive action taken

  7. Feb 13, 2024 · Assembly

    Report passage recommended by Committee on Energy and Utilities, Ayes 12, Noes 4

  8. Feb 13, 2024 · Assembly

    Referred to committee on Rules

  9. Feb 13, 2024 · Assembly

    Placed on calendar 2-15-2024 by Committee on Rules

  10. Feb 14, 2024 · Assembly

    Representative Subeck added as a coauthor

  11. Feb 15, 2024 · Assembly

    Read a second time

  12. Feb 15, 2024 · Assembly

    Ordered to a third reading

  13. Feb 15, 2024 · Assembly

    Rules suspended

  14. Feb 15, 2024 · Assembly

    Read a third time and passed

  15. Feb 15, 2024 · Assembly

    Ordered immediately messaged

  16. Feb 15, 2024 · Senate

    Received from Assembly

  17. Feb 19, 2024 · Senate

    Read first time and referred to committee on Natural Resources and Energy

  18. Apr 15, 2024 · Senate

    Failed to concur in pursuant to Senate Joint Resolution 1