Skip to content

Bills · 2023-2024 Regular Session

SB 481

Died at session end Official bill text Atom feed

Relating to: an incumbent transmission facility owner's right to construct, own, and maintain certain transmission facilities and Public Service Commission procedures if the transmission facility is a regionally cost-shared transmission line.

Electric utility Public service commission

  1. Introduced, stopped here
  2. Passes Senate, not reached
  3. Passes Assembly, not reached
  4. Governor signs, not reached
  5. Law, not reached

Unfamiliar terms? Glossary

What this bill does

Plain-language analysis by the nonpartisan Legislative Reference Bureau

This bill grants to an incumbent transmission facility owner the right to

construct, own, and maintain a transmission facility that has been approved for

construction in the Midcontinent Independent System Operator's (MISO)

transmission plan and that connects to transmission facilities owned by that

incumbent transmission facility owner. Under the bill, an “incumbent transmission

facility owner” is a transmission company or a cooperative or public utility that owns

a transmission facility and provides transmission service in this state. Under

current law, MISO is an organization that is subject to the jurisdiction of the Federal

Energy Regulatory Commission and that coordinates and controls electric

transmission in a region of the country that includes this state. The bill provides that

the right to construct, own, and maintain a transmission facility that connects to

transmission facilities owned by two or more incumbent transmission facility owners

belongs individually and proportionally to each incumbent transmission facility

owner, unless otherwise agreed upon in writing.

The bill also defines “regionally cost-shared transmission line” to mean a

high-voltage transmission line that is eligible for regional cost sharing and is not

subject to a right of first refusal in accordance with the MISO tariff. Under the bill,

if under MISO's transmission plan a regionally cost-shared transmission line has

been approved for construction and connection to facilities owned by an incumbent

transmission facility owner, the incumbent transmission facility owner must give

the Public Service Commission written notice regarding the owner's intent to

construct, own, and maintain the line no later than 90 days after approval of the

transmission plan. If the owner indicates that it does not intent to construct the line,

the bill requires it to fully explain that decision in the notice to PSC. In that case,

the bill allows PSC to determine whether the incumbent transmission facility owner

or another entity must construct the line, taking into consideration issues such as

cost, efficiency, and reliability.

The bill requires an incumbent transmission facility owner with the right to

construct a MISO-approved regionally cost-shared transmission line to include in

any application for a certificate of public convenience and necessity an estimate of

the cost of construction, along with documentation that the estimate is the result of

competitively bid engineering, procurement, and construction contracts. The bill

also requires such an incumbent transmission facility owner to provide to PSC until

construction is complete quarterly reports that include updated estimates of the

construction cost and an explanation of any changes from prior cost estimates.

Sponsors

Introduced by: Bradley (R) , Marklein (R) , Wanggaard (R)

7 cosponsors

Mursau (R) , O'Connor (R) , Petersen (R) , Steffen (R) , Subeck (D) , Swearingen (R) , Wichgers (R)

Votes

Senate: Report passage recommended by Committee on Utilities and Technology, Ayes 4, Noes 1

Passed 4–1 Nov 10, 2023 official source full page

No individual roll call was recorded for this vote. Committee votes and some older sessions record totals only.

Full history

  1. Oct 4, 2023 · Senate

    Introduced by Senators Bradley, Marklein and Wanggaard; cosponsored by Representatives Petersen, Mursau, O'Connor, Plumer, Steffen and Wichgers

  2. Oct 4, 2023 · Senate

    Read first time and referred to Committee on Utilities and Technology

  3. Oct 5, 2023 · Senate

    Representative Swearingen added as a cosponsor

  4. Oct 9, 2023 · Senate

    Public hearing held

  5. Oct 11, 2023 · Senate

    Representative Plumer withdrawn as a cosponsor

  6. Nov 10, 2023 · Senate

    Executive action taken

  7. Nov 10, 2023 · Senate

    Report passage recommended by Committee on Utilities and Technology, Ayes 4, Noes 1

  8. Nov 10, 2023 · Senate

    Available for scheduling

  9. Jan 12, 2024 · Senate

    Senate Amendment 1 offered by Senator Jacque

  10. Feb 15, 2024 · Senate

    Representative Subeck added as a cosponsor

  11. Apr 15, 2024 · Senate

    Failed to pass pursuant to Senate Joint Resolution 1