Bills · 2023-2024 Regular Session
Relating to: an incumbent transmission facility owner's right to construct, own, and maintain certain transmission facilities and Public Service Commission procedures if the transmission facility is a regionally cost-shared transmission line.
Electric utility Public service commission
- Introduced, stopped here
- Passes Senate, not reached
- Passes Assembly, not reached
- Governor signs, not reached
- Law, not reached
Unfamiliar terms? Glossary
What this bill does
Plain-language analysis by the nonpartisan Legislative Reference Bureau
This bill grants to an incumbent transmission facility owner the right to
construct, own, and maintain a transmission facility that has been approved for
construction in the Midcontinent Independent System Operator's (MISO)
transmission plan and that connects to transmission facilities owned by that
incumbent transmission facility owner. Under the bill, an “incumbent transmission
facility owner” is a transmission company or a cooperative or public utility that owns
a transmission facility and provides transmission service in this state. Under
current law, MISO is an organization that is subject to the jurisdiction of the Federal
Energy Regulatory Commission and that coordinates and controls electric
transmission in a region of the country that includes this state. The bill provides that
the right to construct, own, and maintain a transmission facility that connects to
transmission facilities owned by two or more incumbent transmission facility owners
belongs individually and proportionally to each incumbent transmission facility
owner, unless otherwise agreed upon in writing.
The bill also defines “regionally cost-shared transmission line” to mean a
high-voltage transmission line that is eligible for regional cost sharing and is not
subject to a right of first refusal in accordance with the MISO tariff. Under the bill,
if under MISO's transmission plan a regionally cost-shared transmission line has
been approved for construction and connection to facilities owned by an incumbent
transmission facility owner, the incumbent transmission facility owner must give
the Public Service Commission written notice regarding the owner's intent to
construct, own, and maintain the line no later than 90 days after approval of the
transmission plan. If the owner indicates that it does not intent to construct the line,
the bill requires it to fully explain that decision in the notice to PSC. In that case,
the bill allows PSC to determine whether the incumbent transmission facility owner
or another entity must construct the line, taking into consideration issues such as
cost, efficiency, and reliability.
The bill requires an incumbent transmission facility owner with the right to
construct a MISO-approved regionally cost-shared transmission line to include in
any application for a certificate of public convenience and necessity an estimate of
the cost of construction, along with documentation that the estimate is the result of
competitively bid engineering, procurement, and construction contracts. The bill
also requires such an incumbent transmission facility owner to provide to PSC until
construction is complete quarterly reports that include updated estimates of the
construction cost and an explanation of any changes from prior cost estimates.
Sponsors
Votes
Senate: Report passage recommended by Committee on Utilities and Technology, Ayes 4, Noes 1
Passed 4–1 Nov 10, 2023 official source full pageNo individual roll call was recorded for this vote. Committee votes and some older sessions record totals only.
Full history
- Oct 4, 2023 · Senate
Introduced by Senators Bradley, Marklein and Wanggaard; cosponsored by Representatives Petersen, Mursau, O'Connor, Plumer, Steffen and Wichgers
- Oct 4, 2023 · Senate
Read first time and referred to Committee on Utilities and Technology
- Oct 5, 2023 · Senate
Representative Swearingen added as a cosponsor
- Oct 9, 2023 · Senate
Public hearing held
- Oct 11, 2023 · Senate
Representative Plumer withdrawn as a cosponsor
- Nov 10, 2023 · Senate
Executive action taken
- Nov 10, 2023 · Senate
Report passage recommended by Committee on Utilities and Technology, Ayes 4, Noes 1
- Nov 10, 2023 · Senate
Available for scheduling
- Jan 12, 2024 · Senate
Senate Amendment 1 offered by Senator Jacque
- Feb 15, 2024 · Senate
Representative Subeck added as a cosponsor
- Apr 15, 2024 · Senate
Failed to pass pursuant to Senate Joint Resolution 1